Time Value of Money Calculations

Assignment 3: Time Value of Money Calculations

The IT department has requested an update in its server population. This upgrade is required to maintain a competitive position. The CEO has asked that you evaluate the project and submit a recommendation to her, in terms of whether the company should move forward with this request. The calculated value of the project is a reduction of expenses, including power and replacement costs, as shown in Table-1:

 

Year

Decrease in Expenses

1$30,000.00

2$100,000.00

3$120,000.00

4$100,000.00

5$30,000.00

Assume the impact after five years to be immeasurable.  The cost of capital to the firm is currently 8% and the cost of the project today is $286,000.

Required:

  • Calculate the net present value of the project
  • Calculate the internal rate of return
  • Calculate the payback period
  • Calculate the discounted payback period

Submit an Excel file with your calculations, and a 2-to-5-page paper that explains the calculations and provides your final assessment and decision. Justify your recommendations. The paper must be submitted as a Word document and it must follow APA style guidelines

 

You can place an order similar to this with us. You are assured of an authentic custom paper delivered within the given deadline besides our 24/7 customer support all through.

 

Latest completed orders:

# topic title discipline academic level pages delivered
6
Writer's choice
Business
University
2
1 hour 32 min
7
Wise Approach to
Philosophy
College
2
2 hours 19 min
8
1980's and 1990
History
College
3
2 hours 20 min
9
pick the best topic
Finance
School
2
2 hours 27 min
10
finance for leisure
Finance
University
12
2 hours 36 min
[order_calculator]